start
OCTOBER-12-2022
APRIL-18-2023
JUNE-21-2023
JUNE-27-2023
JULY-19-2023
DECEMBER-4-2023
-
end
Project Status:
RE-ZONING AND SPA SUBMISSION
October 11 2022
Project Status:
COMMUNITY CONSULTATION MEETING
April 18 2023
Project Status:
WORKING GROUP MEETING #1
June 21 2023
Project Status:
WORKING GROUP MEETING #1 MEETING SUMMARY
June 21 2023
Project Status:
WORKING GROUP MEETING #2
June 27 2023
Project Status:
WORKING GROUP MEETING #2 MEETING SUMMARY
June 27 2023
Project Status:
WORKING GROUP MEETING #3
July 19 2023
Project Status:
WORKING GROUP MEETING #3 MEETING SUMMARY
July 19 2023
Project Status:
WORKING GROUP MEETING #4
December 4 2023